As Parliament probes the digital number plate contract, the Ministry of Works and Transport maintains that the system was necessary, while questions over procurement, implementation and accountability remain central to the inquiry.

The Ministry of Works and Transport has challenged the context surrounding Ronald Amanyire’s submission before Parliament’s Physical Infrastructure Committee, suggesting that his previous interdiction is relevant to assessing his account of the controversial digital number plate project.

The dispute comes as Parliament examines the contract and the circumstances surrounding the introduction of Intelligent Transport Monitoring System (ITMS) technology, which includes digital number plates and associated vehicle-monitoring infrastructure.

However, the controversy is no longer simply about the credibility of one witness. The parliamentary inquiry has brought broader questions about procurement decisions, implementation, costs and the management of a major public project into focus.

Ministry defends the necessity of digital number plates

In its defence of the project, the Ministry of Works and Transport has maintained that digital number plates were necessary as part of efforts to modernise vehicle identification and monitoring in Uganda.

Speaking before the same committee, the ministry represented by Commissioner Winstone Katushabe further highlights the intended role of the Intelligent Transport Monitoring System, which was designed to support vehicle monitoring and enforcement through digital technology.

The ministry’s position provides an important part of the debate: the rationale for introducing the technology must be distinguished from questions about how the contract was awarded, how it was implemented and whether the arrangements represented value for public money.

A project may have a legitimate public purpose while still requiring scrutiny of the procedures and decisions through which it was delivered.

Amanyire’s submission faces questions over context

The ministry’s challenge to Amanyire’s account introduces his employment dispute into the parliamentary debate. The implication is that his previous interdiction may be relevant to understanding the motivation behind his presentation.

That position, however, should be treated as an argument advanced by the ministry rather than proof that Amanyire’s claims lack merit.

An employment dispute does not automatically invalidate evidence, just as a witness’s allegations do not establish wrongdoing without corroboration. The committee must examine the substance of his submission against contracts, correspondence, financial records and other relevant documentation.

The central question is whether his claims are supported by evidence that can be independently assessed.

Procurement and implementation remain under scrutiny

Reports identify several areas of concern surrounding the digital number plate arrangement, including the procurement process, the project’s implementation and questions about the responsibilities of the parties involved.

These issues require answers beyond the exchange between Amanyire and ministry officials.

Parliament needs to establish how the project was structured, what obligations were assigned to the relevant parties, how implementation decisions were made and whether the contract complied with applicable procurement and public-finance requirements.

It is equally important to distinguish documented findings from allegations or concerns raised during the proceedings. Any conclusion about irregularities or responsibility should follow examination of the available evidence and responses from those concerned.

A necessary technology, but was the contract properly handled?

The ministry’s argument that digital number plates were necessary does not, on its own, resolve questions about the contractual arrangements. Equally, concerns about procurement or implementation do not automatically establish that the technology itself was unnecessary.

These are separate questions that Parliament must address.

The first is whether the system serves a legitimate public purpose. The second is whether the contract was procured, negotiated and implemented in a transparent, lawful and financially responsible manner.

Keeping those questions separate would help the committee avoid allowing personal disputes to overshadow the wider public interest.

Parliament must establish the facts

The Physical Infrastructure Committee now faces the task of reconciling the competing accounts and determining which concerns are supported by evidence.

Amanyire should be required to substantiate his claims, while the ministry should provide documentary explanations for the decisions under scrutiny. Other relevant officials and project stakeholders should also account for their roles where necessary.